The main water shutoff sat right at the corner of our new footing. You find things like that once the old mudroom is gone and you can finally see what you’re working with.
The homeowners stayed in the house through the addition. So the water work had to fit around a home people were using every day, not an empty job site.
First, though, the mudroom had to come apart.
Taking out the mudroom
We took the doors off, saved the shelves and shut off the power. Some of the metal roofing was still good, and I wanted it off in one piece to use again. Whatever had been used to stick those panels together put up a fight. Parts of that mudroom were barely hanging on. Other parts did not want to come apart at all.
Working down from the existing floor
I transferred the floor height to a mark outside and used it as our zero. From there we worked down through the planned floor: 2×10 joists, three-quarter-inch subfloor, and an inch-and-a-half mud sill on an 8-inch concrete block (CMU) stem wall.
That set the relationship between the existing floor, the new framing and the foundation. We also needed concrete showing above the finished grade, with the ground falling away from the building.
Cutting the hill back
The addition was planned to come out about 12 feet from the house. We cut the grade back another eight to ten feet beyond that. There’s a lot of uphill ground behind this house. If we’d dug just enough room for the addition, runoff and snowmelt would still run toward the new foundation. We had the space to cut back farther and give that water a way around the building.
Here, reshaping the ground made more sense than a full French drain. That’s why the excavation runs past the addition’s footprint. We were making room for drainage as well as construction.
The clay in one corner was hard enough that I brought the trencher back. It has carbide teeth for breaking into rock and other hard material. The plan was to gouge the clay loose with the trencher, then clean it out with the bucket.
Getting the water back on
Once we found the shutoff in the footing corner, the plan became moving it outside the new building envelope and rerouting the supply. Part of that new-main work would come later. That day, we had to make the repair and get water back to the house.
The connection did not want to cooperate. It let go twice before the third try held. We cut back the old pipe, added a coupling and remade the connection. I can’t tell you exactly why it took so long to grab. It just wasn’t behaving the way I expected.
We were mostly done with everything else by four or five. The water repair kept us there until after seven. That’s part of working around an occupied house. They needed water, and we got it running. The next morning, it had held all night.
Why we mixed the footing concrete on site

The footing took roughly three yards, a little less by my estimate. A truck couldn’t reach all of it. The batch plant was over an hour away, and the available pump had a long trip in from the other direction.
So we used bagged concrete and a portable mixer.
I know that looks like a lot of handling for a footing. It is. But I’d penciled it out. For this amount, on this site, it cost less and was simpler to schedule than bringing in a truck and a pump. We also had more control. We mixed it as we needed it instead of working with a load that had already spent an hour on the road.
It wasn’t the fastest way to place three yards. It was the practical way for this job.
That was the early part of this addition: working out the elevations, getting the ground to drain, dealing with the water line and picking a pour plan that fit the access. All of it before there was much new space for anyone to look at.