We wanted to keep the useful old barn frame and build a new home around it. The beams and trusses would stay part of the interior. New exterior walls and a new roof would go up over the existing structure, with room above for an insulated attic.
So the first job was separating what we were keeping from what was coming down. We cut the two sections apart before the excavator and dumpsters showed up. You don’t want to start pulling on one part of a building and find out it’s taking the part you meant to save along with it.

Then the ground gave us something else to work through.
A different foundation
It was wet. Really wet. We uncovered a water meter that was still running, which gave us one more thing to look into. We suspected a leak was adding to the saturated ground. But we couldn’t treat that suspicion as the whole answer.
The existing frame needed temporary support while we worked with the engineer on a foundation that suited the site. The revised drawings called for drilled foundations instead of the continuous footing we’d been working toward.
At that stage, the plan was 12-inch-diameter holes, six feet deep, spaced about four feet apart around the building. The idea was to reach harder ground below the poor material near the surface. That layout came from the engineer’s revised drawings for this site.
Drilling gave us the next problem. The holes were full of water and sludge. The auger wouldn’t bring the muck out cleanly. It just slid back off into the hole.
We tried rolling old sheet metal into liners and pushing them down. That let us scoop and pump the mud out without the hole filling right back up. The test looked promising and got the hole much cleaner. So I called a supply house about 26-gauge sheet metal we could cut and roll for the rest of the holes.

The liners had to stay in place through inspection and the concrete pour. A soggy cardboard form wasn’t going to be much help with that. It took some figuring out. The foundation re-engineering cost us almost four weeks before we were moving properly again.

Pricing what the owner could actually picture
I bid the first phase through the foundation, framing and dry-in: windows, doors, trusses and roof sheathing. I hadn’t priced all the finishes, because the owner hadn’t chosen them yet.

Once the rooms started taking shape, those conversations got much easier. You can stand where the kitchen will be, look at the shower layout, and make decisions about the real space instead of trying to picture everything from a drawing.
The owner chose materials while I worked out pricing for the next phase. Dark vertical metal siding, black roofing and stained wood trim were part of those talks. That kept the finish decisions tied to what we were actually building, instead of guessing at them at the start.
Drywall around old beams
Keeping those old beams made for some very particular drywall work.

We had to fit sheets behind the framing we kept, then tape and finish around posts, beams and cables that ran through at angles. A normal straight joint is one thing. Getting a drywall knife into a tight corner behind an angled cable is another.
I could get a room moving along pretty well. Then one of those little intersections would eat up a surprising amount of time. We worked the mud into gaps, wiped it off the old framing before it dried, and figured out where trim could make a cleaner transition while leaving the old wood in view.
Outside, I liked the contrast between the dark cladding and the natural wood. Some of the later finish work was planned for the homeowner, so that handoff was part of the sequence too.
The home was officially complete in May 2025. A lot went into that change from an open barn frame to a home: the foundation work below it, the new structure around it, and all the small places where old and new had to meet.