These old train rails had about six inches of belly in them. They were bowed sideways too. Before we could pour a floor around them, we had to get them straight.
The owner had concrete down both sides of the barn and an unpaved center bay. He wanted that middle filled in so he could park a steel-track excavator and dozer without chewing up the new floor.
The plan was four rails running lengthwise in pairs, sitting just proud of the concrete so the tracks bear on the steel. Getting old railroad iron to sit where you want it is the part that takes the work.
Pulling the rails into position
We set concrete pads with anchor bolts at the rail supports. The pads were roughly 14 to 16 inches deep. We lined the bolts up with a string line and set the elevations with a laser.
The idea was to get the rails between those bolts and cinch them down to the pads. That would pull out the bow and bring them to grade. It worked pretty well. There was still a little variation, but the rails themselves were worn and weren’t all the same height.

Our target was about three-eighths of an inch above the finished slab. A few spots would be a little higher or lower because of that wear. We needed enough projection to catch the equipment tracks.
At the front and back approaches, we went deeper: about 24 inches below the bottom of the rails. That’s where the equipment first loads onto them. There were more deep supports along the run, with the slab concrete filling beneath and around the rails.
The rest of the floor needed preparation too.
Concrete around steel, old and new
We were building an eight-inch slab over granular fill compacted in lifts, with half-inch rebar on an 18-inch grid. We also doweled into the existing concrete at roughly 18-inch intervals. That ties the new slab to the old edges instead of leaving them working independently.
The truck chute could reach partway into the barn, which saved some moving. As the concrete went in, we had to work it underneath the rails, not just fill alongside them and leave a hollow below.
Finishing between the rails
The rails changed the finishing too. A bull float could reach the three wider sections. The narrow strips between the rails had to be worked by hand. One tool wasn’t going to do the whole floor.
I was happy with how it came out. We stopped at a hand-troweled finish that still has some texture, instead of burnishing it to a gloss. A shiny floor looks nice, but this is a barn. In winter, equipment comes in wet, and I didn’t want that surface slick.

At the next-day check, a few things were still ahead of us. We planned to apply a penetrating sealer after about three weeks. The raised rails also left a gap under the door, and we hadn’t yet decided whether it needed extra weather stripping or another detail.
This floor was built around how the owner planned to use it. That drove the supports, the rail height, the way we placed the concrete and the finish we left on top. It was more work than pouring a plain rectangle. That was the point.